Water & powerSaudi Arabia

Rehabilitation, operation and maintenance of nine sewage treatment plants in four regions

A 15-year contract worth more than SAR 1.3 billion to rehabilitate, operate and maintain nine treatment plants in the Northern Cluster, the tenth package of long-term operation and maintenance contracts.

Announced valueMore than SAR 1.3 billion
OwnerNational Water Company (NWC)
PartiesSaudi-Chinese consortium: Armada and Zhangzhou United Waters
StageAgreements signed
Announced

Key details

  • Plants: Unaizah, Al-Bukairiyah, Al-Muznib, Al-Ras, Hail 1, Hail 2, Baqa’a, Sakaka and Turaif.
  • Total design treatment capacity of more than 337,000 cubic metres a day.
  • Tariff of SAR 0.69 per cubic metre.
  • NWC intends to tender 51 existing plants with 888,000 cubic metres a day of capacity this year.

Sources

  1. Saudi Press Agency (SPA) — NWC Concludes a Contract to Rehabilitate, Operate, and Maintain 9 STPs in 4 Regions at More Than SAR1.3 Billion (1 September 2026)

Data as stated in the official announcement at the time; values and dates may change later. Published content is for general information only and is not investment advice.